How ALICE helped Suffolk Construction to Optimize Key Milestones on a Life Sciences Project

Life Sciences Project, USA | Suffolk Construction

The Challenge

Suffolk Construction’s project team was leading the preconstruction and construction planning for a life sciences development project where schedule certainty was critical to project success. 

With the team anticipating that large-scale asset delivery would involve unforeseen constraints and shifting dependencies, Suffolk adopted ALICE during preconstruction to strengthen planning and prepare for deeper schedule analysis, identify bottlenecks, and guide targeted optimization opportunities.

As the project progressed, unforeseen delays driven by procurement challenges and external dependencies threatened a critical milestone.

The project team needed a clear way to diagnose what was driving negative float, validate sequencing assumptions, and identify feasible options to accelerate work without inflating costs or straining field teams.

The Approach

Diagnosing schedule drivers

The project’s Scheduling Director, Dawn Polley, used first ALICE’s Schedule Insights Agent to interrogate the schedule and understand the true drivers of the critical path and uncover optimization opportunities.

ALICE identified that resequencing could accommodate parallel work fronts, enabling earlier and simultaneous installation of multiple equipment units.

Once the team confirmed and adjusted the schedule to bring roof equipment tasks forward, this change alone helped reduce negative float by 22 days.

Identifying targeted productivity opportunities

Additionally, using ALICE’s targeted optimization mode, Dawn evaluated further acceleration options. ALICE surfaced three trade tasks that would drive significant improvement if their productivity increased just by 30%. Focusing on those activities  helped the team recover another 20 days of delay.

Dawn commented, “ALICE delivers real tactical value to our teams by helping us surface optimizations, validate opportunities, and clearly communicate schedule updates and reasoning with stakeholders.”

Aleksey Chuprov, Senior Vice President, Data & IT at Suffolk Construction, added, “Our objective was to recover the delay caused by an external factor and accelerate the overall schedule. ALICE was able to analyze the schedule quickly, to look for opportunities for adjustment.”

Aleksey continued that the value came both from visibility and optimization, emphasizing, “On its own, Insights Agent can create value in just highlighting what can be improved but when connected to the optimization algorithm, it allowed us to save days, to improve productivity by 30 percent.”

Communication and reporting

ALICE’s Schedule Insights Agent and AI difference report were used to generate detailed reports of schedule summaries and optimization drivers along with reasoning including the associated risks and opportunities. This greatly improved confidence and alignment across the entire project team.

 

“On its own, Insights Agent can create value in just highlighting what can be improved but when connected to the optimization algorithm, it allowed us to save days, to improve productivity by 30 percent.”

Aleksey_HS Aleksey Chuprov Senior Vice President, Data & IT

The Results

The Suffolk project team successfully mitigated delays through data-backed decision making and targeted acceleration strategies, recovering a total of 42 days. This optimization strategy effectively eliminated negative float on critical milestones and strengthened control of cost and timeline despite earlier disruptions.

The work also improved coordination and communication across the team by giving everyone a clear, shared view of the schedule and reinforcing Suffolk’s leadership in using advanced technology to drive project certainty.

Aleksey added, “ALICE is the only tool in the market that allows you to leverage AI and model different scenarios, to stack those activities in different ways so you can select and deliver a strategy.”
 
About

Suffolk is a national construction enterprise that provides end-to-end services across the project lifecycle. In addition to construction management, the company offers real estate capital investment, design, self-perform construction services, technology start-up investment through Suffolk Technologies, and innovation research and development.


Location

United States of America


Industry

Industrial

See ALICE in action.

Metrics that matter