SCS_white

SCS JV leverages ALICE to drive £2M savings on the London tunnels of the UK's High Speed 2 Railway

High-speed rail tunnels, United Kingdom | SCS JV

The Challenge

Three major European general contractors – Skanska, Costain, and STRABAG – formed a joint venture, SCS JV, to optimize the construction of the London tunnels of HS2, a national high-speed railway linking London, Birmingham and the north of the country.  The HS2 network will ultimately carry more than 30 million travelers each year. SCS JV is constructing 13 miles of twin-bore tunnels on the HS2 route, terminating at Euston station in central London.

The company has divided its tunnels work into three areas – west, central, and east – and in its initial work with ALICE, SCS JV has focused on the east area, where HS2 emerges from the tunnels on its final 0.6-mile route to Euston station.

In its first work with ALICE, the question at hand for SCS JV was: could it use ALICE to find efficient sequencing options to enable an earlier construction start for the  Euston cavern shaft, which provides critical access to the main tunnels that lead to Euston station.

The Solution

Through “what-if” analysis with ALICE, the SCS JV team was able to identify a number of ways to resequence and improve the build time for the pre-shaft sinking activities.  Changing when they would construct the spoil conveyor, which would remove soil from the excavation and work area, was one such important influencer of the schedule.

SCS JV also determined that they could save time and improve efficiency by having concurrent workforce teams constructing activities to the cavern headhouse base slab, and key milestones, which would enable construction of the cavern shaft earlier than planned.

“The savings of both time and money that we’ve identified with this initial work on SCS East has been significant, and we’re now looking forward to expanding our use of ALICE to other portions of the project.”

Andrew Irwin Construction Manager, Costain Group

The Results

With the ALICE platform, the SCS JV team was able to trim the build time for the shaft by 86 working days, a savings worth £2M in associated overhead expenses.

“Construction optioneering with ALICE has enabled us to quickly and effectively explore alternative ways to build,” said Andy Irwin, SCL Agent at SCS JV. “The savings of both time and money that we’ve identified with this initial work on SCS East has been significant, and we’re now looking forward to expanding our use of ALICE to other portions of the project.”

About

Skanska, Costain, and STRABAG, three prominent European general contractors, joined forces in a collaborative venture known as SCS JV to optimize the construction of the London tunnels of High Speed 2 (HS2), a national high-speed railway that will form the backbone of Britain's transport network.


Location

United Kingdom


Industry

Infrastructure

See ALICE in action.

Metrics that matter

See how ALICE helps the largest GCs and Owners increase their project margins and mitigate risks.

17%
Reduction in project duration
14%
Labor cost savings
12%
Equipment cost savings

See ALICE in action.

Take a custom tour of ALICE and learn why the world's largest General Contractors are using it to optimize their most strategic projects

Book a Demo